OML 60

Working interest 20%
Operator Nigerian Agip Oil Company (NAOC)
Work program Production

Background:

  • OML 60 is located onshore in the Northern Niger Delta. The licence covers an area of approximately 358 km² (88,464 acres).

  • Oil and gas were first discovered within the License area in 1967 in the Akri Field and production started in 1972. Further discoveries were made between 1968 and 1974.

  • To date, the License comprises seven producing fields and two singe well discoveries that have been produced in the past but are currently shut-in.

  • All of the producing fields in OML 60 contain both light and medium sweet crude oil (typically 25° to 45° API), condensates and natural gas.

 
OML 60.jpg

Production Facilities and Infrastructure:

Production and export facilities within OML 60 owned by the NAOC JV include:

  • 94 production and injection wells, of which 24 are currently on production;

  • Flowstation located at Kwale-Okpai (Gross capacity 50-60 mbbls/d)

  • Export pipelines, including a 10/14 inch line linking the Irri, Kwale and Akri fields with the Ebocha oil centre in OML 61, and a 24 inch gas line connecting the Kwale flowstation and Kwale gas plant to the Ob-Ob gas plant in OML 61.